Login or Join
 Learn then Earn
StockMarketNEWS

 news : ‘Railways failed despite investment of Rs 2.5 lakh crore’ #FinanceIndia #StockMarketNEWS #Business New Delhi: Despite investing `2. 5 lakh crore on track infrastructure in the 2008-19 financial

@StockMarketNEWS Tue 12 Apr, 2022

Posted in: #FinanceIndia #StockMarketNEWS #Business

‘Railways failed despite investment of Rs 2.5 lakh crore’ #FinanceIndia #StockMarketNEWS #Business
New Delhi: Despite investing `2. 5 lakh crore on track infrastructure in the 2008-19 financial year, the railways has failed to improve on its mobility outcomes, the CAG has said in its latest report and pulled up the national transporter for avoidable expenses.



In the report submitted in Parliament on Wednesday, the Comptroller and Auditor General of India said the railways’ ‘Mission Raftaar’ scheme too has failed to propel trains on to the fast lane.



“Indian Railways, despite investing `2. 5 lakh crore on track infrastructure during 2008-19, has failed to improve on the mobility outcomes. Mission Raftaar introduced in 2016-17 targeted an average speed of 50 kmph for mail/express and 75 kmph for freight trains by 2021-22. The average observed speed of mail/express and freight trains until 2019-20 was, however, still around 50. 6 kmph and 23. 6 kmph, respectively,??? the CAG said.



It also said that out of 478 superfast trains, the scheduled speed of 123, or 26%, was less than the specified 55 kmph.



“Six main internal critical factors contributing 66% of total detention of trains were identified as controllable. Indian Railways has no guaranteed delivery time for goods consignment. This was due to non-scheduling of goods trains operation,??? it said.



The CAG also said that Dedicated Freight Corridor Corporation of India Limited (DFCCIL) could not fully utilise the World Bank fund resulting in payment of avoidable commitment charges of `16 crore.



“No maintenance facility was created by the DFCCIL. Out of total 4,844  route km, only 2,346 route km (48 per cent) of feeder routes were upgraded till November 2020. DFCCIL incurred avoidable expenditure of `285. 21 crore during the land acquisition process,??? the report stated.



It also said that the progress of the project was affected due to a delay in awarding of contracts.



“There was also a delay in appointment of consultants up to 32 months. DFCCIL incurred avoidable extra expenditure of `2,233. 81 crore till March 2021 towards price escalation. This was due to delay in completion of project,??? it said.



The national auditor also raised the issue of unnecessary and avoidable expenditure incurred by the railways. The railways had incurred avoidable expenditure of `968. 73 crore towards procurement of power from Bhartiya Rail Bijlee Company Limited (BRBCL).



“This avoidable expenditure includes `463. 30 crore towards fixed capacity charges and `505. 43 crore due to injudicious decision to discontinue power purchase agreement with TATA Power-Distribution and procurement of power from BRBCL at higher tariff,??? it said.


Stock Market News & Best Intraday tips & Stocks near support


Report

Login to follow story

More posts by @StockMarketNEWS

0 Comments

Sorted by latest first Latest Oldest Best

 Learn then Earn
Back to top | Use Dark Theme